Main Maintenance facility parking
The Target of the Project • Provide foundation for 2 part concrete paving the first part preparation of soil, provide, • grade and compacting sub base installation then concrete paving installing 8 in (20 cm ) • 4000 psi compressive strength concrete slab approximate area for 8 in 53,170 sqft (4949 • sqm) 2 layers of reinforcing steel .part tow pouring concrete 6 in (15) cm of 3500 psi • area approximate 20,350 sq ft (1,891sqm) designed .provide &install 3 sliding door in • the entrance . • Prime contractor : KBR • Subcontract No : 02H8-US-SJ00263 • Contract value: $329,000.00 • Date of completion 25/11/2005 • Beneficiary side : USA Army • Subcontractor : A- l Mubarak International Group • Location : International Zone Area –Baghdad – IRAQ • Date of Start: 1\10 \2005 • Duration :55 days • Civil works • site preparations • leveling of the site • concrete foundation • steel reinforcements work • Applying crashed stones on the floors • Mechanical works • Supply &Install (3) EA 6 m sliding door .
Al-Mubarak Int Group